New Asphalt Plant, Cliffe Quay Ipswich. |
|
| |
|
|
| |
Tarmac are the client
Jackson are the main contractors and S E H are the sub-contractors who we are working for
Are schedule of works is the formwork ,rebar and concrete.
Most of the walls are constructed using our Doka system and are 6m high ,500mm thick and in pours of 16m long . |
|
| |
|
|
|
|
|